Update | September 8, 2025

30% of the Design Phase is Complete

This summer, the South Cedar Interchange Improved project reached the 30% milestone for the design phase. Throughout this phase, the project team has worked to solidify several critical and foundational project elements, including: 

Horizontal and vertical alignments of the interchange

Interchange roadway configurations

Locations and positions of major project structures

Initial Right-of-Way requirements

The project will soon enter the start of its 60% design phase. In this phase, designers will work to determine:

Sidewalk and park strip alignments

Traffic signal placements

Right-of-Way design 

Utility line relocation

What is "Design-Bid-Build?"

This project follows a "design-bid-build" process, a traditional UDOT project delivery method. This means that the design and construction phases of a project are separated into two distinct contracts. 

The project is in the design contract phase, which will continue through late 2026. This phase determines plans and schedules for project elements such as:

Geotechnical surveying

Roadway alignments

Enviornmental compliance measures

Right-of-Way negotiations and discussions

Final interchange design 

After design plans and specifications are finalized, UDOT aims to advertise the project for a construction bid in the fall of 2026. The construction phase is then 

anticipated to start in the spring of 2027 and continue through late 2028

 

 

For any additional questions on initial survey activity, please reach out to the project team at 435-599-7739 or southcedar@utah.gov.

Schedule

complete
complete
Environmental: May 2023 to December 2024

View the "Schedule" for more information. 

 

live
live
30% Design (Summer 2025)

planned
planned
60% Design (Fall 2025 - Winter 2026)

planned
planned
90% Design (Summer 2026)

planned
planned
Advertise for Construction (Fall 2026)

planned
planned
Construction Anticipated Spring 2027- Winter 2028

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-599-7739

Email: southcedar@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.