This project was completed on November 5, 2025. For questions or more information,
contact UDOT's Region 3 office at 801-227-8000 Monday - Friday 8 a.m. - 5 p.m.
 
2025 Provo Canyon Barrier Safety Project Overview

This project was the second phase of an ongoing effort to improve safety along US-189 in Provo Canyon. Work items included replacing the existing median barrier with improved 42-inch concrete barrier between the north and south travel lanes as well as making drainage improvements.

  • Median barriers help prevent vehicles from crossing over into oncoming traffic, significantly reducing, if not eliminating, the risk of head-on collisions.

  • Crash cushions are installed at the end sections of the barrier as a buffer zone in the case of an accident to help gradually decelerate a vehicle and reduce the force of an impact with a fixed object like the median barrier, ultimately minimizing the severity of injury. See the example below.

      

  • Drainage improvements included installing drains along the median barrier to catch runoff water and direct it away from the road surface. The drain pipes were rehabilitated to improve their efficiency.

Project Map

Schedule

Schedules are subject to change due to weather conditions, material availability, and other unforeseen circumstances.

live
live
This Project Is Complete

complete
complete
End Construction: Late-October 2025

  • All remaining drainage rehabilitation work is complete.
  • Safety improvements like signs and reflectors are installed on or near the new and improved median barrier.
  • Crews clean up all equipment and traffic control devices.

complete
complete
Complete Barrier Installation: Mid-August 2025

  • All of the old median barrier has been removed and replaced with 42" concrete barrier.
  • Concrete has been poured and cured for the new drains along the median barrier. 

complete
complete
Construction Begins: June 2025

  • Crews and equipment mobilize to the work site.
  • Traffic control devices are set up along the corridor.
  • Crews begin removing the old barrier between just east of the Bridal Veil Falls area and Vivian Park.