This project was completed on September 3, 2025.

For questions or more information, contact UDOT's Region 1 office at 801-620-1600 Monday - Friday 8 a.m. - 5 p.m.

 

Project Description:

The Utah Department of Transportation (UDOT) will be implementing safety enhancements of rockfall mitigation on Pineview Dam (SR-158) near Ogden Canyon. The project objectives are aimed at enhancing safety for motorists passing through the route. This work includes using a crane and a helicopter to mount a draped wire mesh fence along the rock wall onto the barrier adjacent to the westbound lane. The results will serve as extra protection from loose falling rocks for SR-158 motorists.

 

See the helicopter installing the Draped Wire-Mesh!  CLICK HERE

 

Completion of Mesh Wire | SR-158 | 08/14/25

Helicopter installation of mesh wire

Helicopter installation of mesh wire | SR-158 | 08/10/25

Map of the Rockfall Mitigation Region on SR-158

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Schedule

Schedules are subject to change due to weather conditions and material availability.

live
live
This Project is Complete

complete
complete
Project Milestones

Workdays: Monday - Friday

Work Hours: Daytime (6am - 8pm)

 

7/21: Construction Start

7/28: SR-158 Full closure. Helicopter to install mesh wire.

8/15: SR-158 reopened to traffic

9/2: SR-158 Roadway maintenance.  Expect one-way alternating traffic on job site

9/3: Construction End