UPCOMING CONSTRUCTION ACTIVITIES:*

 

  • Crews will continue to place power meters and will install concrete vaults along Redwood Rd. at various locations between 5400 S and 4100 S. during the winter months.
  • Please view the map in the Project Overview section below for Phase details.
  • New construction activities are expected to take place on the east side of Redwood Rd. from approximately 5400 S. to Smiley Dr. over the next two weeks.
  • Crews will remove and replace the sidewalk, place new conduits, and will remove all existing walls in this area. Temporary fencing will be installed prior to removal of the old walls, which will be coordinated with each property owner.
  • Crews will begin to remove fence and other items to prepare for earthwork on the west side of Taylorsville High School.

 

Pedestrians are asked to follow all posted detours and to remain out of constructions zones for safety. 

 

*Construction schedules are subject to change due to utility, material, weather, or equipment delays. 

 

SURROUNDING BUSINESSES & RESIDENTS CAN EXPECT:

 

  • Construction activities 5 days per week
  • Lane shifts and traffic delays 
  • Increased noise, dust, and vibration
  • Construction crews and equipment in the area
  • Two lanes of traffic open in each direction

 

PROJECT OVERVIEW

 

Taylorsville City in coordination with the Utah Department of Transportation (UDOT), plan to improve mobility and safety along Redwood Road between 4100 South and 5400 South (Taylorsville City, Utah). This corridor has a significant amount of traffic and experiences vehicle conflicts, crashes and congestion due to its many commercial and public accesses. The purpose of this project is to improve traffic flow and safety, remove obstructions near the road and enhance the Redwood Road corridor.

ENHANCEMENTS INCLUDE:

  • Installation of right-turn pockets 

  • Consolidation of commercial and public accesses

  • Removal and reconstruction of curb and gutter, driveways, sidewalks, pedestrian ramps, roadway signage

  • Installation of pavement markings, drainage modifications and utility relocations

  • Relocation of overhead powerlines and power poles underground

  • Installation of bus pullouts, pedestrian benches and shelters at the UTA bus stops

  • Installation of wider park strips and improved aesthetics with landscaping​

 

CONTACT US

 

Email: redwoodroadmobility@utah.gov

Hotline: 855-663-6800

Website: https://publicinput.com/redwoodroadmobility

Schedule

July 2022: Contruction Begins

Spring 2023: Construction Ends

*Construction activity is weather, materials, and equipment-dependent and subject to change

 