Overview

Project Description

To extend the life of 700 East (State Route 71), the Utah Department of Transportation (UDOT) will resurface the asphalt, replace existing raised medians, and upgrade non-compliant ADA pedestrian ramps along 700 East (SR-71) between 400 South and 1700 South in Salt Lake City. Construction began Monday, July 13, 2026. This work will help keep the road smooth, last longer, and make your daily drive more comfortable.

No major changes to the design of the road are expected. The same number of lanes will remain when the project is completed.

 

What to Expect:

Impacts will include traffic shifts, lane closures, intermittent access limitations and an increase in nighttime noise. Bike lanes will be closed and there will be no on-street parking during construction. Drivers should expect delays and use alternate routes when possible. 
 

What you’ll see after construction:

  • A smoother roadway built to last another 5–10 years
  • Improved safety for all road users 

 

This is the project area map of the repaving of 700 East between 400 South and 1700 South

 

 

Sign up to receive weekly email updates using the form at the bottom of this page. 

Contact Information

Sign up to receive weekly email updates

Construction Timeline

 

Project Timeline

planned
planned

Construction: Summer - Fall 2026

Construction will begin July 13, 2026

Monday - Saturday

8 p.m. to 6 a.m.

complete
complete

Advertisement: March 2026

The project will be advertised to contractors beginning in late March 2026.

complete
complete

Design: Fall 2025 through Spring 2026

The team designed improvements and reached out to any potential property owners about impacts. 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 855-925-2801 #12095

Email: 700epaving@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.