On Thursday, May 15, crews will fix rumble-strips, apply a second layer of pavement marking and finish thermoplastic markings throughout the project area. The new right-turn lane has a speed limit of 5 miles per hour; please slow down and use caution when exiting right off of SR-318. 

Crews will return in the Fall of 2025 to place native vegetation seeding in designated areas. 

Refer to the photos below for more detail. 

Update: 4.30.25

Crews are applying microsurfacing to SR-318 to improve road texture and longevity. Refer to photos below for more detail. 

Update 4.14.25

Refer to progress photos below. 

Update: 3.17.25

Refer to progress photos below. 

Schedule

complete
complete
Design: 2024

Property coordination and design for these improvements were completed in 2024. 

live
live
Construction: February to May 2025

Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-531-1358

Email: quaillake@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.

udotinput.utah.gov/quaillake