Project Overview

 

The Utah Department of Transportation (UDOT) will be resurfacing Center Street in Provo to extend the life of the roadway from 500 West to Geneva Road (SR-114). In addition, pedestrian ramps will be reconstructed within the construction area. On-street parking along Center Street between Geneva Road and I-15 will no longer be permitted.

Nighttime paving is currently scheduled to happen from June 12th through August 25th between the hours of 9:00 p.m. and 7:00 a.m. 

Schedule

live
live
Construction: Summer 2023

Work Begins: June 12, 2023
Work Ends: Fall 2023
Work Days: Monday - Friday
Daytime: 7:00 a.m. - 9:00 p.m.
Nighttime: 9:00 p.m. - 7:00 p.m. Some nighttime work will take place for paving and related items along Center Street.

Schedules are subject to change due to weather conditions and material availability.

 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 800-948-8286
Email: provocenterstpaving@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.