The roadway between University Avenue and 500 West was reconstructed in a similar layout as previous projects on U.S. 89 in Provo have done. Thie project improved the roadway and underground infrastructure and provided better transportation options for all kinds of road users.

 

 

Project Activities*:

The Provo 300 South project completed all major items ahead of schedule. This includes all lanes of 300 South and the intersection of 500 West. We've come a long way in the last 9 months!

 

Crews will still be onsite through mid-December as they work on project-wide cleanup and final restoration items.

 

 

 

 

 

 

The Utah Department of Transportation (UDOT) is constructing improvements for US-89 (300 South) in Provo between University Avenue and 500 West. The project is improving the road and underground infrastructure while providing better transportation options for all kinds of road users.

 

The project team is improving the corridor by:

  • Replacing 300 South asphalt with concrete pavement
  • Upgrading the roadway drainage system with storm drain, curb and gutter
  • Replacing aged underground utilities including sewer and culinary water
  • Adding new pedestrian/bicycle crosswalks in several locations
  • Widening the sidewalk on both sides of 300 South
  • Reconstructing driveway approaches
  • Adding on-street bicycle lanes
  • Installing "bump-outs" on 400 West to reduce the crossing distance at intersections without painted crosswalks
  • Installing raised medians between blocks to improve safety
  • *In locations with existing buildings at the back of sidewalk, widening may be required if or when those properties are redeveloped.
 
The map below shows the project area.

 

Cross-section of 300 South

complete
complete
Design

Summer 2023

complete
complete
Project Advertisement

A contractor has been selected

live
live
Construction

February 14, 2024

FOR IMMEDIATE PUBLIC INQUIRIES

Project Hotline: 888-556-0232

Email: provo300s@utah.gov