The roadway between University Avenue and 500 West will be reconstructed in a similar layout as previous projects on U.S. 89 in Provo have done. This will improve the roadway and underground infrastructure while providing better transportation options for all kinds of road users.

 

 

Project Activities*:

 

  • The intersection of 500 West/300 South remains closed while crews excavate in preparation for concrete. This closure will be in place for approximately three more weeks due to some unforeseen utility conflicts. Freedom Boulevard to 500 West is open to local traffic while Freedom Boulevard to University Avenue is open to all traffic. Freedom Boulevard is open to north/south traffic.
  • Crews continue hand-pouring sidewalks, ADA ramps, and driveway tie-ins through next week.

New concrete looking east

 

Impacts:

Homeowners can expect open trenching and intermittent access limitations during this work. One lane in each direction will be open on 300 South. Work will take place Monday through Friday from 7 a.m. to 5 p.m. unless noted.

 

 

The Utah Department of Transportation (UDOT)has designed improvements for US-89 (300 South) in Provo between University Avenue and 500 West. The project's goals are to improve the road and underground infrastructure while providing better transportation options for all kinds of road users. The project will begin in early February.
 
The project plans to reconstruct the road between University Avenue and 500 West in a similar layout as previous projects on U.S. 89 in Provo (500 West and 300 South) have done.
 
The project team plans to improve the corridor by:
  • Replacing 300 South asphalt with concrete pavement
  • Upgrading the roadway drainage system with storm drain, curb and gutter
  • Replacing aged underground utilities including sewer and culinary water
  • Adding new pedestrian/bicycle crosswalks in several locations
  • Widening the sidewalk on both sides of 300 South
  • Reconstructing driveway approaches
  • Adding on-street bicycle lanes
  • Installing "bump-outs" on 400 West to reduce the crossing distance at intersections without painted crosswalks
  • Installing raised medians between blocks to improve safety
  • *In locations with existing buildings at the back of sidewalk, widening may be required if or when those properties are redeveloped.
 
The map below shows the project area.

 

Cross-section of 300 South

complete
complete
Design

Summer 2023

complete
complete
Project Advertisement

A contractor has been selected

live
live
Construction

February 14, 2024

FOR IMMEDIATE PUBLIC INQUIRIES

Project Hotline: 888-556-0232

Email: provo300s@utah.gov