Overview

Project Overview

The Utah Department of Transportation (UDOT) will be improving Payson Main Street (State Route 115) from State Route 198 to Benjamin Cemetery. The road will be resurfaced to preserve the life and help increase the longevity of the road. A portion of this project from 100 N to 600 N will be restriped to add a Center Turn Lane that will improve safety. Adding a center turn lane will make the road safer and more predictable for drivers. The new turn lane will provide a dedicated space for left-turning vehicles to wait outside the through lane, reducing sudden stops and improving traffic flow.

  • Please provide your public input about the restriping of SR-115 on the 'Public Comments' tab.

 

Project Map

Map of the Payson Main Street Project - showing paving area and the addition of the Center Turn Lane

Project Map of Payson Main Street Improved

Stay Informed

To receive occasional construction email updates, please enter your information below:

Construction Schedule

Work Hours: Sunrise - Sunset

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live
Design: Spring/Summer 2026

Winter/Spring 2026: Striping Design Underway

Spring 2026: Public Outreach to adjacent stakeholders to provide public comments.

planned
planned
Construction: Spring/Summer 2027

Construction Start: As early as March 2027

Estimated Completion: August 2027

  • The project will include full road resurfacing and road restriping to add a Center Turn Lane

complete
complete
Project Milestones

Winter 2026: Striping Design

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8363

Email: paysonmain@utah.gov

Stay Informed

To receive weekly construction updates, please fill out the form at the bottom of the Overview Tab or email the public information team at paysonmain@utah.gov with "Updates" in the subject line.