This project was completed on December 5, 2025. For questions or more information, contact UDOT's Region 3 office at 801-227-8000 Monday - Friday 8 a.m. - 5 p.m.

 

Nephi Main Street Paving Project Overview

UDOT resurfaced Main Street in Nephi City from the junction with I-15 on the north end of the city to the I-15 junction on the south end.

Resurfacing activities included asphalt removal and replacement along five miles of Main Street. This project preserved and extended the life of the pavement which improves motorist safety by providing good traction and skid resistance for vehicles. Crews also reconstructed the sidewalk, curb, and gutter between 600 South and 700 South on the east side of the road, replaced and installed new ADA (The Americans with Disabilities Act) compliant ramps along the corridor to improve pedestrian safety and access, installed new storm drain pipe at 700 South, and replaced concrete waterways at 300 South and 1500 South to improve drainage in the area.

 

Project Map

Schedule

Work Hours: 7 a.m. - 7 p.m.

Work days: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

live
live
This Project is Complete

complete
complete
Concrete Work: May to December 2025

  • Replaced pedestrian ramps along Main Street to bring them up to current ADA standards.
  • Replaced driveways, curb, and gutter intermittently along the corridor to improve storm water drainage.
  • Installed and then later replaced concrete waterways at 300 South and 1300 South to improve drainage in these areas.

Concrete can take up to two weeks to cure before traffic can drive on it.

 

complete
complete
Paving: August to September 2025

  • Prior to paving, crews lowered utilitiy manholes beneath the surface of the road.
  • Mid-August, crews paved side street entrances off of Main Street to tie-in the old asphalt with the new.
  • Crews patched back the asphalt around the newly installed waterways and pedestrian ramps.
  • Mainline paving on Main Street started Monday, August 18. This took approximately four weeks to complete.

complete
complete
Construction Begins: May 2025