Overview

Project Overview

We are improving SR-113 at 400 East (River Road) in Midway by installing a four-way signal with dedicated turn lanes, pedestrian access with crosswalks, and bike lanes. These changes aim to streamline traffic, reduce delays, and make the intersection safer for motorists and active transportation users.

Key Features of the Project Include:
• New four-way traffic signal at SR-113 and 400 East (River Road)
• Dedicated turn lanes to improve traffic flow
• Pedestrian access improvements with marked crosswalks
• New bike lanes to support active transportation users

Construction Impacts:
Motorists can expect to be shifted into open lanes as necessary. Be prepared to stop for one-way traffic-light operations. There may also be full closures along 400 East (River Road) at times; detour routes will be posted. Please anticipate light delays between 5–10 minutes. Alternate pedestrian access will be available during construction. Some light to moderate noise from equipment can be expected. Two-way travel will remain in place during non-working hours and holidays.

 

**One-way alternating traffic will be in place on Midway Main Street from 300 East to 500 East from the beginning of March through mid-May. At this time, the intersection entrance at 400 East and/or 500 E and Main Street will be closed during daylight hours. Additionally, the intersection at 400 E and Main will be closed during all hours until 04/20/26. Please use caution when approaching the construction zone and slow down for crews and traffic control.

Map of Project Area/SR-113 River Road

SR-113 / River Road Construction Area Map

Stay Informed

To receive occasional construction email updates, please enter your information below:

Contact Information

To contact the public information team with questions or concerns:

 

Stay Informed

To receive email updates, please fill out the form at the very end of the Overview tab or email the public information team at MidwayMain400E@utah.gov and type "Updates" in the subject line.

**You are signing up for updates from all Heber Valley projects.

Active Construction

Hours: Mostly Daytime work

Workdays: Monday - Friday

No work on Sundays or holidays (Saturdays only as necessary)

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live
Weekday Traffic Impacts: April 13 - April 17

  • During Construction Hours:
    • One-way alternating traffic will be maintained, guided by traffic lights.
    • There will be construction traffic on 300 E as crews install underground utilities.
  • At All Times:
    • Road shoulders and indicated sidewalks are closed to pedestrians and parking within the project area at all times.
    • The intersection at 400 E and Main will be closed night and day until 04/20/26. Please use an alternate route.

live
live
Construction Phase: Late Winter - Summer

Schedule *

*Schedules outlined below are subject to change due to weather conditions and material availability.

live
live
Active Construction

  • 2/23/26 | Work began at job site; Side-walk deconstruction began. Road sidewalks and shoulders closed. 
  • 03/02/26 | Daytime flagging operations are intermittently in place as crews prepare utilities for roadway reconstruction.
  • 03/09/26 | Additional daytime closures in-place (500 E and 400 E intersections). One-way alternating traffic measures put in place.
  • 03/15/26 | One-way alternating traffic control continues through mid-May.

planned
planned
Planned Construction

  • Mid-Late March 2026: Main Roadway Excavation, Pole-Removal and Utility Work
  • Late-March - Early April: Water utility work: Water system shut-offs will be necessary. Each affected property will receive notice beforehand

complete
complete
Project Milestones

  • Work in project-area began on 03-03-2026