US-91 | Mantua | Bridge Work
US-91 | Mantua | Bridge Work
Preserving the Mantua Bridge deck to extend its lifespan and prevent costly repairs, ensuring long-term travel reliability.
This project was completed in November 2025.
For questions or more information, contact UDOT's Region 1 office at 801-620-1600 Monday - Friday 8 a.m. - 5 p.m.
Project Description
We carried out critical preservation work on the Mantua Bridge deck in both directions. This project was designed to extend the bridge’s service life and prevent the need for more extensive—and costly—repairs in the future. By addressing wear and tear early, UDOT enhanced safety, improved long-term travel reliability, and delivered cost-effective solutions for Utah taxpayers.
Construction began in late March. Since then, crews worked to remove deteriorated surface materials, perform structural repairs, and prepare the bridge for resurfacing.
During construction, lane closures were in place; however, at least one lane in each direction remained open at all times to maintain traffic flow. Drivers experienced delays, particularly during peak travel hours, and were encouraged to plan ahead, reduce speed, and exercise caution through the work zone.
Paving Prep Work looking WB 07/11/25
Installed Approach Slabs (Looking West on the WB side) 06/26/25
Mantua Bridge Reconstruction (Looking West on the EB side) | 06/26/25
Mantua Bridge Deck Demolition (Looking West) | 04/25/25
Schedule