Skip Navigation
 

Logan Canyon | US-89 & SR-243 | Technology

Logan Canyon | US-89 & SR-243 | Technology

Updates

Watch the video below to learn more about the project.

 

2025 Project Highlights


Construction Update | Nov. 5, 2026

21397_Excavator beside a steel-covered pavement opening along U.S. 89 in Logan Canyon, surrounded by autumn trees and mountainous terrain.

An excavator sits beside a steel-covered pavement opening along US-89 in Logan Canyon, surrounded by autumn trees and mountainous terrain.

21397_Logan Canyon - Asphalt Paving Work

Asphalt pavement along US-89 in Logan beside two utility junction box covers set in a concrete pad on the gravel shoulder, with forested canyon slopes beyond. 


Upcoming Construction Activities

Crews anticipate finishing connections between sections of fiber-optic cable over the next week, weather permitting before the project enters it's winter hiatus. The splicing process joins the cables so data can travel continously through the fiber network. 

Traffic control equipment will be removed from the roadway as crews wrap up this season's work next week. Drivers are encouraged to slow down and use caution near crews until work is complete. Remaining work will resume in spring 2027. This will be our final email update for the season, with updates resuming ahead of spring construction activities.

The project email and hotline will continue to be monitored throughout the winter. Please reach out with any questions. 

* Construction schedules are subject to change due to weather, utilities, and material delays.


A Look Below the Ground: What is Conduit?

Much of the Logan Canyon fiber project takes shape beneath the surface. The pipes shown in the photo are called conduit, which provides protective pathways for fiber-optic cables.

How deep does it go? Depths vary throughout the canyon. In the lower canyon part of the canyon, conduit is buried as deep as 5ft. Above Right Hand Fork, depths range from approximately 2-3ft. depending on the installation method and location.

Before installing fiber, crews check that the conduit is clear so cables can pass through. Once underground work is complete, the trench is backfilled and the surface restored, leaving much of the project's infrastructure out of sight. 

 

10,000 Tons of Asphalt - and Counting!

Crews have placed approximately 10,000 tons of asphalt as part of the roadway restoration work in Logan Canyon to date. That's more than 20 million pounds, the equivalent of approximately 400-500 typical asphalt truckloads.

21397_Logan Canyon Fiber Work

Crew member uses a compactor to pack soil in a narrow trench

along US-89 in Logan Canyon, with an excavator behind them. 

CAUTION: Motorcyclists, Cyclists, and Drivers

There are trenches, uneven road surfaces, and loose gravel throughout the corridor. Please use caution and prioritize safety while travelling through the construction area. Reduce speed, follow posted signage, and be alert of crew members and equipment.

The project is utilizing one-way traffic systems to manage vehicle flow through the work zones. Drivers utilizing turnouts within the project area are advised to wait until seeing vehicles traveling in the same direction of your destination before safely re-entering the travel lane.

Aerial view of a two-lane highway winding through a steep mountain canyon. Construction vehicles, including trucks and an excavator, are parked along the roadside within a coned work zone. Dense green trees and shrubs fill the canyon floor, while rocky slopes rise on both sides under a bright blue sky with scattered clouds. PIN 21397

Aerial view of  construction trucks and excavators along US-89 in Logan Canyon, with traffic cones marking the work zone between steep, rocky mointainsides.

21397_Logan Canyon Fiber Work

Red, blue and gray conduit runs through a narrow trench between concrete walls,with portions covered by backfill material along US-89 in Logan Canyon.


2025 Fun Facts

The project team has been hard at work! See the information below for some fun facts about the project this year.

  • 22 crew members installing conduit on the field and approximately 48 team members behind-the-scenes
  • 325 junction boxes installed
  • 700 feet of directional drilling completed under the Logan River
  • Approximately 28 miles of conduit installed (including different depths of trenches)
  • Clean fast rock saw operation – 26" deep, 88,000 feet (fiber only)
  • Rock saw trench – 48” deep, 16,000 feet (fiber + Rocky Mountain Power)
  • Primary running line – 60” deep, 10,000 feet (fiber + City of Logan Power)

 

​Road construction activity in a mountainous canyon along a two-lane highway. An orange sign reading “One Lane Road – Wait for Traffic Flow Before Proceeding” stands beside parked construction trucks and equipment. A vehicle travels through the work zone as traffic barrels guide drivers along the roadway. Steep rocky slopes and dense green vegetation line both sides of the canyon beneath a clear blue sky. PIN 21397

Driver's view of construction trucks and traffic barrels along US-89 in Logan Canyon, with a sign reading "One lane Road–Wait for Traffic Flow Before Proceeding". 


Work Zone Map


Know Before You Go! Download the UDOT Traffic App Today!


The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways.

 

The available information includes:

  • Emergency and incident notifications
  • Construction alerts
  • Anticipated delays and lane closures
  • Road conditions
  • Travelwise alerts
  • A zoomable, scrollable map-based display


*download available for iPhone and Android devices

Learn more about Travelwise Tips here.

Schedule

Workdays:

Daytime work Monday - Friday

  • Occasional weekend work

*Construction schedules are subject to change due to weather, utility and material delays.

Project Timeline

live
live

Construction Spring 2025-2027

planned
planned

Project Completion (Spring 2027)

complete
complete

Project Milestones

  • Final Design (2024)

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-996-7086

Email: logancanyonfiber@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.