Skip Navigation
 

SR-162 & SR-262 | San Juan County | Improved

SR-162 & SR-262 | San Juan County | Improved

Overview

Construction Complete

This project was completed on August 14, 2026.

Questions?

UDOT Region 4 office 435-893-4799
Mon - Fri, 8:00 a.m. - 5:00 p.m.

 

Project Introduction

UDOT and Navajo Nation Logos 

 

The Utah Department of Transportation (UDOT), in partnership with the Navajo Nation, received a Nationally Significant Federal Lands and Tribal Projects Grant. The grant was used to improve safety on SR-162 and SR-262 in San Juan County, Utah. Additional federal and state funding was approved, and the project duration from March 2024 to August 2026.

Project Purpose and Improvements

The project objectives were intended to improve safety and pavement along 53 miles of road in San Juan County between SR-162 and SR-262. Additional improvements included rebuilding multiple structures and other roadway-specific enhancements. This project made travel safer, smoother, and more convenient for:

  • Residents in the area
  • Visitors traveling to Bears Ears, Four Corners, and Hovenweep National Monuments
  • Workers serving the petroleum extraction industry in the region

The following is a shortlist of key upgrades that was completed:

  • Improved pavement
  • Improved and/or installation of safety features such as guardrail, cattle guards, extra signage, protected turn lanes, and pavement markings
  • Widened lanes and/or add shoulders
  • Rebuilt or improved several dozen culverts and flood mitigation infrastructure
  • Built a roundabout at the SR-162 and SR-262 intersection
  • Replaced the SR-162 bridge over McElmo Creek
  • Installed fiber-optic conduit
  • Installed over 50 cattle guards at various roadway access points
  • Built a livestock crossing under SR-162

Map showing construction area of SR-162/SR-262 from Bluff to Colorado boarder. UDOT PIN 17894

 

SR-262 Guardrail Installations | 01/14/26

 

McElmo Bridge Deck Forms.

McElmo Bridge Deck Forms | 06/24/25

 

Montezuma Creek Roundabout Grading

Montezuma Creek Roundabout Sub-Grading | 06/24/25

 

Three construction workers assembling headwall and culvert with the road of SR-262 above them.

Culvert Extension and Headwall Assembly | SR-262 | 02/10/25

 

Shoulder Extension to prepare for road widening, showing dirt on side of the road on SR-262.Shoulder Extension to prepare for road widening, showing dirt on side of the road on SR-262.
Shoulder Extensions | SR-262 | 02/10/25

 

 

New cattleguard with construction barrels around it and construction equipment behind.

Completed Cattle guard Installation | SR-162 @ Montezuma Creek | 02/10/25

 

Side of the road on SR-262 trenched out with an excavator in the background in order to install Fiber optic cable.

Trenching for Fiber Optic Conduit Installation | SR-262 | 02/10/25

Project Timeline

live
live

This Project is Complete

complete
complete

Project Milestones

 

  • Contractor advertising (March/April 2024)
  • Contractor awarded (May 2024)
  • Groundbreaking event (August 13, 2024)
  • 70% of paving completed in 2025; work resumes in 2026
  • McElmo Bridge completed (November 2025)
  • Cattleguards installed (January 2026)
  • Roundabout grand opening (February 2026)
  • Guardrails installed and complete (April 2026)
  • Fiber optic cable installation complete (May 2026)
  • Roundabout downlighting operational (June 2026)
  • All paving objectives completed on SR-162/262 (June 2026)
  • Project completion (August 2026)