TRAFFIC NOTICE: SR-162/262 intersection bypass active. See "Traffic Impacts" tab for more details

 

UDOT | Navajo Nation_Logo 

Project Introduction

The Utah Department of Transportation (UDOT) in partnership with the Navajo Nation has received a Nationally Significant Federal Lands and Tribal Projects Grant. The Grant will be used to improve safety on SR-162 and SR-262 in San Juan County, Utah.  Additional federal and state funding has been approved with work tentatively scheduled to continue through 2026.

Project Purpose and Improvements

The project objectives are intended to improve safety and pavement along 53 miles of road in San Juan county between SR-162 and SR-262.  Additional improvements include the rebuild of multiple structures, and other roadway specific enhancements. This project will make travel safer, smoother and more convenient for the residents in the area; visitors traveling to Bears Ears, Four Corners, and Hovenweep National Monuments; and workers serving the petroleum extraction industry in the region.  The following is a shortlist of several key upgrades:

  • Improve and/or reconstruct pavement
  • Improve and/or install safety features such as guardrail, cattleguards, extra signage, protected turn lanes, and pavement markings
  • Widen lanes and/or add shoulders
  • Rebuild or improve several dozen culverts and flood mitigation infrastructure
  • Construct a roundabout at the SR-162 and SR-262 intersection
  • Replace the SR-162 bridge over McElmo Creek
  • Install fiber-optic conduit
  • Install over 50 cattleguards at various roadway access points
  • Construct a livestock crossing under SR-162

 

McElmo Bridge Deck Forms Image

McElmo Bridge Deck Forms | 062425

 

Montezuma Creek Roundabout Grading

Montezuma Creek Roundabout Sub-Grading | 062425

 

Job Site Photo 262

Culvert Extension and Headwall Assembly | SR-262 | 021025

 

Shoulder Extension ImageShoulder Extension Image
Shoulder Extensions | SR-262 | 021025

 

 

Cattleguard Image

Completed Cattleguard Installation | SR-162 @ Montezuma Creek | 021025

 

Fiber Optic Image

Trenching for Fiber Optic Conduit Installation | SR-262 | 021025

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Schedule Icon  Schedule

complete
complete
Pre-Construction 2024

  • Contractor Advertising (March/April)
  • Contractor Awarded (May)
  • Groundbreaking Event (Aug 13)

Navajo Nation - Aneth Chapter Logo

live
live
Construction Start: mid-August 2024

Work Hours: 7am - 7pm 

Workdays: Monday - Friday (No Holidays)

(Updated as of 6/25/25)

SR-262

US-191 to Montezuma Creek:  Paving activity complete through this 22-mile route.  Centerline rumblestrips to be installed in early July.  Traffic control will be required at up to rolling 1-mile flagging and pilot car operations to maintain safety for crews.  Fiber optic install continues heading toward Montezuma Creek.  Motorists should expect up to 5 min. delays at each flagging location.

SR-162

Bluff to Montezuma Creek:  Off-road work continues.  Occasional local traffic control may be necessary.  Delays should be light.

Montezuma Creek to Aneth:    A full reconstruct of the road surface continues with paving completed through the first 5 miles from Montezuma Creek.  Be cautious while traveling as the entire depth of asphalt has been removed in sections.  Bumps in the road transitioning from asphalt to dirt.  Be prepared to hold for a flagging and pilot-car operation.  Please plan on up to 10 minutes delays.

Aneth to Colorado Border:  Paving complete, with centerline and shoulder rumble strips to be installed in early July.  Plan on some one-way alternating traffic delays.

SR-162 | McElmo Creek Bridge

Bridge deck forms in place.  Concrete bridge deck to be poured with short-distance flagging operation on Thursday night, June 26.  Traffic remains open on old bridge.

SR-162/262 | Montezuma Creek Roundabout

The new roundabout construction is underway with the sub-grading nearly complete.  Traffic bypass detour active.  Please see the "Traffic Impacts" Tab for more details.

planned
planned
Construction End: Summer 2026

Schedules are subject to change due to weather conditions and material availability.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8364

Email: sr162-262@utah.gov

Website: udotinput.utah.gov/sr162-262