UDOT | Navajo Nation_Logo

 

Project Introduction

The Utah Department of Transportation (UDOT) in partnership with the Navajo Nation has received a Nationally Significant Federal Lands and Tribal Projects Grant. The Grant will be used to improve safety on SR-162 and SR-262 in San Juan County, Utah.  Additional federal and state funding has been approved with work tentatively scheduled to continue through 2026.

Project Purpose and Improvements

The project objectives are intended to improve safety and pavement along 53 miles of road in San Juan county between SR-162 and SR-262.  Additional improvements include the rebuild of multiple structures, and other roadway specific enhancements. This project will make travel safer, smoother and more convenient for the residents in the area; visitors traveling to Bears Ears, Four Corners, and Hovenweep National Monuments; and workers serving the petroleum extraction industry in the region.  The following is a shortlist of several key upgrades:

  • Improve and/or reconstruct pavement
  • Improve and/or install safety features such as guardrail, cattleguards, extra signage, protected turn lanes, and pavement markings
  • Widen lanes and/or add shoulders
  • Rebuild or improve several dozen culverts and flood mitigation infrastructure
  • Construct a roundabout at the SR-162 and SR-262 intersection
  • Replace the SR-162 bridge over McElmo Creek
  • Install fiber-optic conduit
  • Install over 50 cattleguards at various roadway access points
  • Construct a livestock crossing under SR-162

 

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Map showing construction area of SR-162/SR-262 from Bluff to Colorado boarder. UDOT PIN 17894

McElmo Bridge Deck Forms.

McElmo Bridge Deck Forms | 06-24-25

 

Montezuma Creek Roundabout Grading

Montezuma Creek Roundabout Sub-Grading | 06-24-25

 

Three construction workers assembling headwall and culvert with the road of SR-262 above them.

Culvert Extension and Headwall Assembly | SR-262 | 02-10-25

 

Shoulder Extension to prepare for road widening, showing dirt on side of the road on SR-262.Shoulder Extension to prepare for road widening, showing dirt on side of the road on SR-262.
Shoulder Extensions | SR-262 | 02-10-25

 

 

New cattleguard with construction barrels around it and construction equipment behind.

Completed Cattleguard Installation | SR-162 @ Montezuma Creek | 02-10-25

 

Side of the road on SR-262 trenched out with an excavator in the background in order to install Fiber optic cable.

Trenching for Fiber Optic Conduit Installation | SR-262 | 02-10-25

Schedule Icon  Schedule

complete
complete
Pre-Construction 2024

  • Contractor Advertising (March/April)
  • Contractor Awarded (May)
    • Groundbreaking Event (Aug 13)

Navajo Nation - Aneth Chapter Logo

live
live
Construction: Aug. 2024 - Spring 2026

Work Hours: 7am - 7pm 

Workdays: Monday - Friday (No Holidays)

Schedules are subject to change due to weather conditions and material availability.

(Updated as of 9/18/25)

SR-262

US-191 to Montezuma Creek:  Paving activity complete.  Varied work requiring short-distance traffic control will be required to maintain safety for crews as they work on bridges.   Motorists should expect up to 5 min. delays at each flagging location.

SR-162

Bluff to Montezuma Creek:    Some shoulder widening activity is ongoing requiring a short flagging and pilot car operation.  There may be as many as two flagging and pilot car operations along this route.   Paving anticipated by late-Sept.  Delays may be 10-15 minutes, with up to 20 minutes during peak periods

Montezuma Creek to Aneth:    Heavy paving work in Montezuma Creek is complete.  However, the full reconstruct of the road surface continues between Montezuma Creek and Aneth.  Be cautious while traveling as the entire depth of asphalt has been removed in one-mile sections.  Bumps in the road transitioning from asphalt to dirt.  Be prepared to hold for a flagging and pilot-car operation.  Please plan on up to another 15 minutes delays during peak periods.

Aneth to Colorado Border:  Plan on occasional shoulder operations as necessary.  No delays are anticipated.

SR-162 | McElmo Creek Bridge

Traffic now moving over bridge with approaches from either side under construction. 

SR-162/262 | Montezuma Creek Roundabout

The new roundabout construction is ongoing.  Pavement to be applied starting 9/17.  Traffic bypass detour remains active.  Current delays are running in excess of 10 minutes during peak periods.   (Update) Traffic will not begin through the roundabout until the lighting is powered up and the lane striping is complete.  DATE TBA

Please see the "Traffic Impacts" Tab for more details.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8364

Email: sr162-262@utah.gov

Website: udotinput.utah.gov/sr162-262