Project Overview

The Utah Department of Transportation (UDOT) is starting a major construction rehabilitation project on I-215 West from SR-201 to North Temple. Project Elements include:

  • Roadway reconstruction
  • Rehabilitation of 22 bridges
  • Pavement reconstruction on 14 miles of ramps on I-80 and California Avenue

If you have any questions, comments, or concerns, please call the project information line at: 855-215-UDOT

Traffic Impacts*

Ongoing

  • Intermittent overnight lane closures will affect both Northbound and Southbound I-215 throughout the end of September
  • The ramp from Redwood Road near I-80 to I-215 NB is closed through October. Please follow the posted detour or consider an alternate route
  • I-215 NB is reduced to 3 lanes that are shifted to the east and will remain in place through October
  • I-215 SB is reduced to 3 lanes that are shifted to the west and will remain in place through October

Construction Activities

  • In the center of I-215, crews are installing pipes and drain boxes for the new drainage system
  • Once the new drainage system is installed, crews will prepare the middle of 215 for asphalt paving in late September

What to Expect

  • Lane closures and traffic shifts
  • Heavy equipment, support vehicles, and crew members
  • Delays

 

Project Map

*Schedules are subject to change.

 

Schedule

* July 28, 2025 - Fall 2026

 

Schedules are subject to change due to weather conditions and material availability.

live
live
Construction

Lane Closures and construction activities July 2025 - Fall 2026

planned
planned
Project Completion (Fall 2026)

complete
complete
Project Milestones

Construction begins July 28, 2025

Contact Information

To contact the public information team with questions or concerns:

Hotline: 855-215-UDOT

Email: i215westimproved@utah.gov

 

Stay Informed

To receive weekly construction updated, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.