Project Overview

The Utah Department of Transportation (UDOT) is starting a major construction rehabilitation project on I-215 West from SR-201 to North Temple. Project Elements include:

  • Roadway reconstruction
  • Rehabilitation of 30 bridges
  • Pavement reconstruction on 14 miles of ramps on I-80 and California Avenue

 

Upcoming Traffic Impacts*

I-80 Lane and Ramp Restrictions

  • Both directions of I-80 near I-215 will be reduced to one lane on the evenings of Thursday (March 19), Friday (March 20), and Monday (March 23) from 9 p.m. through the early morning hours.
  • During these times, expect intermittent ramp closures.

California Avenue Road Closure

  • California Avenue, under I-215, will be full closed from Friday, March 27 at 9 p.m. through Saturday, March 28 at 6 a.m.
  • The on and off-ramps at California Avenue will remain open, but left-turn movements at the interchange will be restricted.

I-215 Southbound California Avenue Off-ramp and On-ramp Closure

  • As early as April 23, for approximately 3 weeks, the Southbound I-215 California Avenue off-ramp and on-ramp will be closed.
  • Use SR-201 as an alternate route to access the area.

I-215 Northbound California Avenue Off-ramp and On-ramp Closure

  • As early as July 28, for approximately 3 weeks, the Northbound I-215 California Avenue off-ramp and on-ramp will be closed.
  • Use SR-201 as an alternate route to access the area.

 

Upcoming Traffic Impacts: I-215 / I-80 Interchange Ramps*

As part of the I-215 and I-80 interchange, 11 bridges in this area need to be improved. To allow for a safe construction zone and to provide an efficient construction duration, the ramps in this area will close between April through August*. Details of each ramp closure are included below. During these closures, please allow extra time when traveling in the area or consider an alternate route.

*Construction schedules are subject to change.

 

Where

Redwood Road to Northbound I-215 and Westbound I-80

When

Early April for approximately 30 days

 

Where

Southbound I-215 to Westbound I-80

Eastbound I-80 to Southbound I-215

Redwood Road to I-215 Southbound

Westbound I-80 to Southbound I-215

When

Early May for approximately 40 days

 

 

Where

Westbound I-80 to Northbound and Southbound I-215

Eastbound I-80 to Northbound I-215

Southbound I-215 to Eastbound I-80

When

Early June for approximately 30 days

 

 

Where

Northbound I-215 to Redwood Road

Northbound I-215 to Eastbound I-80

Northbound I-215 to Westbound I-80

When

Early July for approximately 30 days

 

 

Where

Eastbound I-80 to Redwood Road

Northbound I-215 to Redwood road

When

Early August for approximately 20 days

 

Ongoing I-215 Traffic Impacts*

  • All traffic is shifted to the east side of I-215 through next Summer.
  • Expect overnight lane and ramp closures.

 

Ongoing Local Street Traffic Impacts*

The bridges over each of the streets below are being rehabilitated. Expect various restrictions during construction activities. 

    Cross Street Closures

    • 500 South: 500 South is restricted to one lane in each direction and lane shifts through the end of March
    • Indiana Avenue: Expect intermittent traffic restrictions and lane shifts through the end of March
    • California Avenue: Expect intermittent turning movement restrictions and lane shifts through the end of March
    • 1700 South: Expect intermittent traffic restrictions and lane shifts through the end of March

     

    Ongoing Construction Activities 

    • Construction activities continue to progress on the west side of I-215 including:
    • Installation of a new drainage system
    • Placement of barrier
    • Removal of the road surface
    • Demolition of the top layers and sides of various bridges

     

    What to Expect

    • Lane closures and traffic shifts
    • Reduced speeds
    • Noise, dust, and vibration
    • Heavy equipment, support vehicles, and crew members in the area

     

    Project Map

    *Construction schedules and traffic impacts are subject to change.

     

    Schedule

    * July 28, 2025 - Summer 2027

     

    Schedules are subject to change due to weather conditions and material availability.

    live
    live
    Construction

    Lane Closures and construction activities July 2025 - Summer 2027

    Contact Information

    To contact the public information team with questions or concerns:

    Hotline: 855-215-UDOT

    Email: i215westimproved@utah.gov

     

    Stay Informed

    To receive weekly construction updated, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.