This project was completed on August 31, 2025. For questions or more information, contact UDOT's Region 2 office at 801-975-4900 Monday - Friday 8 a.m. - 5 p.m.

 

Project Overview

The Utah Department of Transportation (UDOT) improved I-215 eastside from 4500 S. to 2000 E. This project spanned from Murray City to Millcreek City and included concrete repairs and shoulder work. This work improved safety, enhanced durability, and increased the lifespan of the road. This work began in mid-April and was completed at the end of August 2025.*

 

What to Expect

  • Nighttime work 
  • ​8 p.m. – 6 a.m. 
  • Occasional weekend work 
  • Moving operations, shifting travel lanes and occasional ramp closures
  • Noise, dust, construction lights, and vibrations.
  • Heavy equipment, support vehicles, and crew members in the area
  • Minor delays

* Construction schedules are subject to change due to weather, equipment, labor or material delays.

 

Schedule

complete
complete
This Project is Complete

complete
complete
Construction: April - September 2025

Work Hours: 8 p.m. - 6 a.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

 

Check UDOT Traffic today!

The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways.

 