Overview

Project Overview

The Utah Department of Transportation (UDOT) has transitioned the I-15 Santaquin to Payson project from the environmental phase into project delivery.

This project plans to widen I-15 to three lanes in each direction from south of Santaquin to Payson and reconstruct the I-15 Santaquin Main Street Interchange, including improvements to nearby Santaquin roads (see Santaquin Main Street Reconfiguration Map on the map tab), to improve traffic operations and safety, increase capacity, and enhance community connections. When finished, I-15 will have three travel lanes in each direction from Spanish Fork to northern Juab County.

This project is utilizing the Design-Build process, which leads to faster project delivery, greater flexibility, and is a better value for state funds. See the “What is Design-Build?” tab for more on this process.

UDOT preliminary design and fieldwork are actively underway, and construction is anticipated to begin as early as summer 2027. See the project timeline underneath the project map for more details.

Project Map

Map showing the Interstate 15 project area spanning from northern Juab County up to 800 South in Payson, highlighting key locations including Rocky Ridge, Summit Ridge Parkway (Exit 242), Santaquin and Main Street (Exit 244), Spring Lake, and Payson (Exit 248). PIN 21601

Project Timeline

Timeline graphic showing the project schedule from spring 2026 through winter 2028. UDOT Design runs from spring 2026 through spring 2027. Contractor Design begins in summer 2027 and continues through winter 2027–28, overlapping with the start of Construction. Construction begins in spring 2028 and continues through winter 2028. PIN 21601

Schedule

Project Timeline

live
live

Active work

  • UDOT gathering data to complete 30% preliminary design

planned
planned

Future steps

  • Design-build contractor selection: Anticipated spring 2027
  • Concurrent final design & construction: Anticipated summer 2027 to late 2028

complete
complete

Project milestones

Environmental assessment: Winter 2023-2025

  • Finalized environmental document in March 2025

  • Hosted fall 2024 public hearing and public comment period

    Contact Information

    Stay Informed

    To receive construction updates, please contact the public information team at the email address above and enter "Updates" in the subject line.