I-15 Safety Project from MP 18-22 on I-15 both North and Southbound

This project will improve safety features along I-15 in Washington County, UT by removing and replacing the wildlife fencing throughout this area. In addition, another cattleguard will be placed at the northbound off-ramp at Exit 22 in Leeds, UT. (see map)

The project will take approximately three months to complete. Work will start on Monday, November 4.

The cattleguard installation is expected to complete by Friday, November 22, with the exception of a few final improvements. Refer to the progress photos below for more detail. 

**Schedule is subject to weather and other unforeseen circumstances**

Updated progress on the secondary cattle guard installation (see above). 

Updated progress on the secondary cattle guard installation (see above)

 

Schedule: November 2024 to February 2025

live
live
Construction: November 2024 to February 2025

Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday

Removal and replacement of wildlife, safety fencing adjacent to I-15 from MP 18-22, Hurricane, UT to Leeds, UT. 

At the northbound I-15 off-ramp at Exit 22, crews are currently installing an additional cattleguard. Watch for changing traffic patterns during construction. The exit will remain open, but the roadway will be shifted to accommodate the work. The installation began the first week of November 2024, and is expected to complete by November 22, with the exception of a few final improvements. 

complete
complete
Design: 2023 to 2024

Wildlife Safety Fence Improvements - November 4, 2024 to February 28, 2025

Add another cattleguard to the northbound, I-15 off-ramp at Exit 22. 

Design for this project has been completed. 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-531-1358

Email: i15safetyproject@utah.gov