I-15 Safety Project
I-15 Safety Project
Starting Monday, November 4, 2024, The Utah Department of Transportation (UDOT) began removing and replacing the wildlife safety fencing along I-15 starting in Hurricane and ending in Leeds, UT - Mile Post (MP) 18-22. The work takes place outside of the I-15 travel lanes.
Another safety improvement adds an additional cattleguard at the northbound, I-15 off ramp at exit 22. Traffic patterns will be changing as this work progresses. The cattleguard installation began the first week of November 2024, and is expected to complete the first week of December 2024.*
Crews will be working Monday through Friday from 7 a.m. to 6 p.m.
All of these improvements are anticipated to be completed by mid-February 2025.*
*Schedule is subject to weather and other unforeseseen circumstances.
I-15 Safety Project from MP 18-22 on I-15 both North and Southbound
This project will improve safety features along I-15 in Washington County, UT by removing and replacing the wildlife fencing throughout this area. In addition, another cattleguard is being placed at the northbound off-ramp at Exit 22 in Leeds, UT (see map). The work takes place outside of the I-15 travel lanes.
Starting Monday, November 4, 2024, The Utah Department of Transportation (UDOT) began removing and replacing the wildlife safety fencing along I-15 starting in Hurricane and ending in Leeds, UT - Mile Post (MP) 18-22.
The cattleguard installation began the first week of November 2024, and is expected to complete the first week of December 2024.*
Crews will be working Monday through Friday from 7 a.m. to 6 p.m.
All of these improvements are anticipated to be completed by mid-February 2025.*
*Schedule is subject to weather and other unforeseseen circumstances.
Refer to the progress photos below for more detail.
UPDATED 11/26/2024
Work on the new cattle guard is nearing completion. Crews continue to improve safety along the I-15 Corridor from MP 18-22 with the installation of new wildlife fencing. These activities will not impact I-15.
Work on the project will be suspended from Wednesday, November 27 at noon to Monday, December 2 at 7 a.m.
Updated progress on the secondary cattle guard installation (see above).
Updated progress on the secondary cattle guard installation (see above)
Schedule: November 2024 to February 2025
Contact Information
To contact the public information team with questions or concerns:
Hotline: 435-531-1358
Email: i15safetyproject@utah.gov