I-15 Safety Project
I-15 Safety Project
Starting Monday, November 4, 2024, The Utah Department of Transportation (UDOT) will begin removing and replacing the wildlife, Safety fencing along I-15 starting in Hurricane and ending in Leeds, UT - Mile Post (MP) 18-22. This work will take place outside of the I-15 travel lanes.
Another safety improvement will add an additional cattleguard at the northbound, I-15 off ramp at exit 22. Traffic patterns will be changing as this work progresses. It is anticipated the cattleguard installation will start the first week of November 2024 and be completed by mid-December 2024.*
Crews will be working Monday through Friday from 7 a.m. to 6 p.m.
All of these improvements are anticipated to be completed by mid-February 2025.*
*Schedule is subject to weather and other unforeseseen circumstances.
I-15 Safety Project from MP 18-22 on I-15 both North and Southbound
This project will improve safety features along I-15 in Washington County, UT by removing and replacing the wildlife fencing throughout this area. In addition, another cattleguard will be placed at the northbound off-ramp at Exit 22 in Leeds, UT. (see map)
The project will take approximately three months to complete. Work will start on Monday, November 4.
The cattleguard installation is expected to complete by Friday, November 22, with the exception of a few final improvements. Refer to the progress photos below for more detail.
**Schedule is subject to weather and other unforeseen circumstances**
Updated progress on the secondary cattle guard installation (see above).
Updated progress on the secondary cattle guard installation (see above)
Schedule: November 2024 to February 2025
Contact Information
To contact the public information team with questions or concerns:
Hotline: 435-531-1358
Email: i15safetyproject@utah.gov