Project Description

Coming in 2026, the Utah Department of Transportation (UDOT) will repair ten bridges at five locations along I-15 by either replacing or rehabilitating the bridge decks.   In addition to the bridge deck work, the project may include leveling the approaches and bringing barriers up to current standards. 

Project Preparation work is underway.  A culvert will be installed under the Hall Loop Road bridge.  Bypass roads located along the inside of various bridges will be constructed through Spring 2026.  Once complete, bridge rehabilitation work will begin on the bridges.  (See latest Impacts & Updates Tab Above)

 

 

Map of the Levan Bridges Project 2025-2026 showing the construction areas from Elwood Road to Hall Loop Road.

2026 Levan Bridges Project Route

 

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Schedule

Work Hours: Daytime Hours

Workdays: Monday - Thursday (Updated - Schedule through April 2026)

 

Schedules are subject to change due to weather conditions and material availability.

live
live
Construction - Winter 2026 - Fall 2026

  • Winter/Spring 2025-26 - Culvert & Bypass Work [Phase 1]

Off-road work continues periodically along the route building bypass roads at prescribed locations. Culvert construction at Hall Loop Rd.: 2/16 - 4/1

  • Spring/Summer 2026 [Phase 2] - Bridge Reconstruction
  • October 2026 - Estimated Project Completion

Bridge Construction work will begin in the Spring of 2026 with approximately 7 months to complete.  Additional information TBA.

[ See Impacts & Updates Tab ]

planned
planned
Milestones

  • February 16 | Culvert construction begins at Hall Loop Rd.

complete
complete
Project Design: 2024 - 2025

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8363