Skip Navigation
 

I-15 | Hamilton Fort | Rebuild

I-15 | Hamilton Fort | Rebuild

UDOT is adding a northbound climbing lane on I-15 between the Kanarraville Rest Stop and the South Cedar Interchange. This project is also improving the Hamilton Fort Interchange at Exit 51.

Overview

Project Overview

The Utah Department of Transportation (UDOT) plans to construct a 13-mile-long northbound climbing lane on I-15 from the Kanarraville rest stop to the South Cedar Interchange, milepost 43 to 56. The project will widen I-15 through this area from two to three northbound lanes. The project will also reconstruct the northbound side of the Hamilton Fort interchange (Exit 51) with a roundabout constructed on the east side of I-15.

Construction is expected to require multiple construction seasons, beginning in Spring 2025 and ending in early 2027. Construction schedules are subject to change due to weather conditions and material availability.

To join our email list for project updates, visit the "Sign Up for Updates" tab.

Progress at Exit 51

At the Hamilton Fort Interchange (Exit 51), crews are nearing completion of the new bridge and have started excavation work for the new roundabout. 
They have built a temporary bypass ramp to allow traffic to access northbound I-15. The image below shows an aerial view of the newly paved bypass. The image was taken on August 27, 2026.

Drone image of the Exit 51 Interchange and newly paved bypass ramp onto NB I-15. PIN 18224

Schedule

Work Hours: 6 a.m. - 5 p.m.

Work Days: Monday through Friday

There may be intermittent one-lane closures on I-15 during nighttime work hours of 7 p.m.- 7 a.m.

Project Timeline

live
live

Construction

Construction began in Spring 2025. 

Traffic is shifted on northbound I-15 as crews build a third passing lane between mileposts 43 and 56. 

Earthwork is underway on the east side of I-15 near the Hamilton Fort Interchange as crews build a new roundabout. 

Crews are rebuilding the west side of the bridge at Hamilton Fort on northbound I-15. 

Schedules are subject to change due to weather conditions and material availability.

planned
planned

Project Completion

The project is anticipated to be completed in Late Fall 2026

complete
complete

Design

Project design was completed in Winter 2024.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-254-3305

Email: i15hamiltonfort@utah.gov

Stay Informed

To receive project updates, please contact the public information team at the email address above and enter "Project Updates" in the subject line.