PROJECT OVERVIEW
The Utah Department of Transportation (UDOT) will widen Geneva Road (SR-114) from University Parkway (SR-265) to 1450 South to include two travel lanes in each direction and a center turn lane. Additional improvements will include a bike lane in each direction, a 10-foot-wide multi-use path on the east side and a sidewalk on the west side. Construction is underway and is expected to be completed by late 2026.
PROJECT UPDATE
Utility work is underway along Geneva Road and will continue through winter 2025, causing intermittent shoulder closures.
Additional work will include:
- Drainage and irrigation work: Fall 2025 through spring 2026
- Road widening: Early 2026 through late 2026
- Pedestrian features: Fall 2026
WHAT TO EXPECT
- Work Monday through Friday during daylight hours
- One travel lane in each direction
- Shoulder closures
- Increased noise and vibration, intermittently
- Pedestrian detours as needed
CONTACT INFORMATION
If you have any questions, please contact a project representative using the information listed below:
Hotline: 385-323-2001
Email: genevaroad@utah.gov