UDOT repaved approximately 15 miles of asphalt on SR-44 this summer from Manila to Milepost 13 in Daggett County. This project also included replacing a culvert underneath the road near Milepost 22, repairing soft spots in the asphalt, replacing guardrail and barrier as needed to improve safety, and updating road signs along the corridor.

Schedule

complete
complete
Culvert Replacement - May 15 to mid-June 2024

Work Hours: 7 a.m. - 5 p.m.

Work Days: Monday - Friday

Schedules are subject to change due to weather or other unforeseen circumstances.

Culvert replacement activities will take place at Milepost 22, approximately 6 miles south of Manila. Motorists can expect one-way traffic operations during work hours.

complete
complete
SR-44 Paving - June to September 2024

Work Hours: 7 a.m. - 7 p.m.

Work Days: Monday - Friday

Schedules are subject to change due to weather or other unforeseen circumstances.