September 21, 2023

 

Paving

Paving along the main roadway of SR-18 is complete. Future work will now include working on updating side street roadway and drive approaches for a smooth transition from side roads onto SR-18. This will take place the remainder of September and will continue throughout October.

Striping

The SR-18 main line roadway will begin to be striped the remainder of September and will continue throughout October.

Additional

Painting, lane delineators and rumble strips will be placed throughout the project over the next few weeks. There will be traffic control elements in place during installation.


 


Project Overview

The Utah Department of Transportation (UDOT) is improving the roadway on State Route 18. The work is divided into two areas: Ledges to Diamond Valley and Veyo to north of Central.
This project is a roadway asphalt rehabilitation project and will also make various improvements at different locations along SR-18, these include:

  • Pedestrian access ramps
  • Roadway and shoulder widening
  • Concrete barrier replacement
  • Dedicated turn lanes
  • Addition of two-way left turn lanes

Project Area Map

Contact Us!

Project Hotline: 866.777.1850

Project Email: sr18improved@utah.gov