Safety Message: The sidewalks within the project limits are closed to pedestrians. The project is detouring pedestrians to the following route (see map below) for safety. Please stay out of the work zone for your safety and our crews' safety.

 

 

University Avenue prepped for paving

Project Activities: Aug 2

 

  • Crews continue excavating the road on the east side of the intersection. Traffic has been shifted to the west and motorists are advised to pay attention to traffic control.
  • Beginning Friday, August 2, crews will begin paving concrete along the east side of University Avenue.
  • Beginning next week, crews will begin to prep for new curb and gutter on the south side of Canyon Road followed by concrete pours the following week.
  • Beginning next week, crews will remove the old signals at the intersection in preparation for new signal installation.
complete
complete
Design

planned
planned
Construction

June 2025