Project Description

The Utah Department of Transportation (UDOT) will resurface State Route 35 in Summit County from Francis to twelve miles east near Nobletts Trailhead. The project objectives are aimed at preserving the life of the roadway. This paving process will help increase the longevity of the road surface, address roadway deterioration, and enhance motorist safety by resmoothing asphalt that can’t be corrected with patching.  Refreshed lane and roadway painting/striping will be applied following the work, as well as updated roadside signage.  Update:  Noblett's trailhead will NOT be paved this season.

 

Latest Update (10/28):  Final inspection has been completed. 

 

 Site Visit 10/30/2024 |Optical Speed Bars--these are meant to visually help drivers to slow down and draw attention to the curve

 

SR-35 | Francis to MP 8 Paving Photo

Site Visit 10-16-2024

 

SR-35 | Francis to MP 8 Paving Map

 

Schedule

complete
complete
Construction Start: August 8th

Work Hours: 7am - 7pm; 7am - 3pm (Fridays)

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

  • Through 10/9: Crews adding gravel material to road shoulders.
  • Through 10/11:  Lower utiliity covers along route. Continue upgrading guardrail at various locations.
  • Through 10/24: Striping of travel lane lines and intersection stop-bar lines.  Installation of upgraded roadside signs.

complete
complete
Construction End: October 24, 2024

Project duration will be approximately 70 days. Please check back for additional details on progress.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8362

Email: kamasfrancispaving@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.