Main Street (SR-13) Asphalt Rehabilitation Project
The Utah Department of Transportation (UDOT) will rehabilitate the asphalt pavement on Main Street (SR-13) through Brigham City from 1100 South (US-91) on the south to I-15 on the north. The project also includes upgrading selected pedestrian sidewalk ramps to meet current Americans with Disabilities Act (ADA) standards.
Key Highlights:
This project involves removing old asphalt and placing new pavement called “Bonded Wearing Course” to enhance this critical route which links the city with I-15 and other Box Elder County municipalities. It involves:
ADA Ramp Upgrades: Modifications ensure sidewalk transitions are accessible to everyone.
Adjusting Manholes: Lowering utility accesses (ie. manholes and water valves) to allow for milling.
Edge Milling: Removing old asphalt which will make the roadway rough temporarily.
Paving: Applying Bonded Wearing Course for a smooth finish.
Raising Manholes and Valves: Adjusting utility access points to the new roadway surface.
Roadway Striping: Applying final paint for striping/crosswalks/messages to new pavement.
Schedule & Impacts:
Pedestrian Ramps: Daytime work where possible Monday through Friday 7am to 7pm. Nighttime work in locations were right turn lanes do not exist Monday through Friday 7pm to 7am
Roadway: Nighttime work Sunday through Thursday 8pm to 7am.
Temporary sidewalks closures during ped ramp demolition and reconstruction.
Lane shifts and temporary lane closures during construction.
Business access remains open.
- Nearby residents will notice construction-related noise and vibration.
Schedule
Contact Information
To contact the public information team with questions or concerns:
Hotline: 800-292-3557
Email: SR13paving@utah.gov
Stay Informed
To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.