Project Overview

We are committed to maintaining the safety and reliability of bridges throughout the state. The Structures Division has identified three bridges in Box Elder County requiring maintenance, repairs, or replacement to ensure public safety.

Key Highlights:

This project will involve three bridges in Box Elder County at the following locations:

  • 1000 North over I-84 at Garland/Bothwell Interchange (EXIT 39)

Project: Bridge Deck Replacement

Timeline: October 1, 2024 through December 19, 2024

Impact: Full closure of this bridge for 2-3 months. Detours will be in place.

  • SR-102 over I-84 at Tremonton/Bothwell Interchange (EXIT 40)

Project: Bridge Deck Replacement

Timeline: Spring 2025 through Summer 2025

Impact: Full bridge closure from May 31, 2025 through August 24, 2025

  • 18400 N over I-84 at Pocatello Valley Interchange (EXIT 24)

Project: Full Bridge Replacement

Timeline: Spring 2025 through Fall 2025 

Impact: Full closure for 6-7 months with detours to adjacent interchanges.

 

Nearby residents will notice construction-related noise and vibration.

 

Schedule

Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

live
live
Construction

Crews will return in the spring/summer to complete a chip seal application one the new bridge decks.

complete
complete
Design: 2023-2024

Contact Information

To contact the public information team with questions or concerns:

Hotline: 800-292-3557

Email: boxelderbridges@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Updates" in the subject line.