The Utah Department of Transportation (UDOT) is committed to maintaining the safety and reliability of bridges throughout the state. The Structures Division has identified three bridges in Box Elder County requiring maintenance, repairs, or replacement to ensure public safety.
Key Highlights:
This project will involve three bridges in Box Elder County at the following locations:
1000 North over I-84 at Garland/Bothwell Interchange (EXIT 39)
Project: Bridge Deck Replacement
Timeline: October 1, 2024 through December 19, 2024
Impact: Full closure of this bridge for 2-3 months. Detours will be in place.
Crews will complete work on the 1000 North bridge this fall. Construction will be suspended over the winter months with work resuming on the two remaining bridges in early spring 2025.
SR-102 over I-84 at Tremonton/Bothwell Interchange (EXIT 40)
Project: Bridge Deck Replacement
Timeline: Spring through Fall 2025
Impact: Expect alternating one-way traffic controlled by temporary signals at each end of this bridge.
18400 N over I-84 at Pocatello Valley Interchange (EXIT 24)
Project: Full Bridge Replacement
Timeline: Spring through Fall 2025
Impact: Full closure for 6-7 months with detours to adjacent interchanges.
Nearby residents will notice construction-related noise and vibration.
Schedule
Contact Information
To contact the public information team with questions or concerns:
Hotline: 800-292-3557
Email: boxelderbridges@utah.gov
Stay Informed
To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Updates" in the subject line.