Interstate 80; Emory to Castle Rock Paving Project

The Utah Department of Transportation (UDOT) resurfaced Interstate 80 from Emory (Milepost 178.8) to Castle Rock (Milepost 184.6) in Summit County.  Work included milling and paving the corridor and the eastbound on ramp at the Castle Rock Interchange and applying a top coat  throughout the corridor and on the ramps at the Castle Rock interchange.. The work is being done to extend the life of the pavement and provide a smoother driving surface.  

Construction is substantially complete.  

Schedule

complete
complete
Design: 2022

complete
complete
Construction: June 11, 2023 to July 18, 2023

Construction is substantially complete. 

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.