Final SES

In the SES UDOT proposes to widen Andelope Drive between the West Davis Corridor interchange and 2000 West to include five lanes east of the interchange. A new traffic signal would be installed at 2500 West and right-turn lanes would be included at 2500 West and 2000 West. Each side would also have a 5-foot bike lane, 7-foot shoulder, curb, gutter, and a 5-foot wide sidewalk.

The final SES is available for download below.

We have also included the materials that were provided at the public meetings.

Study Area

Map of Antelope Dr with shaded area between 4500 W and 2000 W.

complete
complete
Scoping - Spring 2019

Conduct scoping and accept comments.

complete
complete
Develop Purpose and Need - Spring 2019

Define project objectives and the transportation challenges associated with Antelope Drive.

complete
complete
Develop and Screen Alternatives - Spring 2019

Develop a range of solutions, identify environmental resources, and select a build alternative to evaluate in detail.

complete
complete
Analyze Impacts of Alternatives - Summer 2019

Evaluate build alternative; quatify the effects to the social, economic, and natural environment.

complete
complete
Prepare Draft SES - Fall 2019

Draft SES available for public review; a hearing was held to solicit public comment on the Draft SES.

complete
complete
Final SES and Decision - Winter 2019

Respond to public input; finalize SES and issue decision.