Final Construction Update | December 12, 2024

 

This week, crews will be forming and constructing the side walls (parapet) on the north end of the Adams Avenue Bridge. This work is to enhance safety along the bridge and tie the parapet wall into the guard railing on the westbound on and off-ramps.

 

Project inspection and clean up will take place after this work. No future work is scheduled after this week.

 


 

Project Overview

The Utah Department of Transportation (UDOT) will be removed and replaced the existing deck of the Adams Avenue bridge over I-84 in Weber County. Additional construction activities included miscellaneous structural improvements and updating the drainage system. This project enhanced safety and will continue to preserve the life of the bridge. 

 

Schedule                                                  

  • Construction began - Spring 2023
  • Project completed - Winter 2024

Updated Adams Avenue Map_June 2023

complete
complete
Final Design (2022)

complete
complete
Construction Began (Spring 2023)

Work Hours: 7 a.m. - 5 p.m. 

  • Occasional nighttime work

Work Days: Monday-Saturday 

*Construction schedules are subject to change due to utility, material, weather, or equipment delays. 

live
live
Project Completion (Winter 2024)

Contact Information

The project team is here to assist, please call or email with any questions:

Hotline: 855-740-8740

Email: adamsavenuebridge@utah.gov 

 

Stay Informed

Want the latest? Sign up for email updates by emailing adamsavenuebridge@utah.gov with "Subscribe" in the subject line. 


Project impacts to travel can be found on the UDOT Traffic Website, www.udot.utah.gov/traffic or by downloading the UDOT Traffic app.