UDOT is replacing two existing culverts that cross beneath SR-147 (7300 South) just west of 4850 West in Benjamin. Construction will consist of removing and replacing the larger box culvert for Benjamin Slough and a smaller pipe culvert near the intersection to improve drainage in the area. Work is expected to begin as soon as August 21, 2023.

 

During work hours, Monday through Friday between 7 a.m. and 7 p.m., and occasionally on weekends as needed, you can anticipate lane closures, one-way flagging operations, detours, and moderate traffic delays. There will also be increased noise, dust, and vibrations typically associated with construction.

Sign up for updates by sending us an email with “SR-147 Culverts” in the subject line to stay up to date with our schedule.

live
live
Start Construction: August 21 2023

Work hours: 7 a.m. to 7 p.m.

Work days: Monday - Friday, and occasionally on weekends as needed

Schedules are subject to change due to weather conditions and material availability.

complete
complete
SR-147 ROAD CLOSURE

SR-147 (7300 South) between the Benjamin Slough and 4850 West from September 5 through September 19.

Work will take place day and night for 15 consecutive days.

Schedules are subject to change due to weather conditions and material availability.

planned
planned
End Construction - October 2023

Contact Information

To contact the public information team with questions or concerns:

Hotline: 385-557-2585

Email: udotregion3@utah.gov

Stay Informed

To receive construction updates, please contact the public information team at the email address above and enter "SR-147 Culverts" in the subject line.