Overview

Project Description

To extend the life of 700 East (State Route 71), the Utah Department of Transportation (UDOT) will resurface the asphalt, replace existing raised medians, and upgrade non-compliant ADA pedestrian ramps along 700 East (SR-71) between 400 South and 1700 South in Salt Lake City. Construction is expected to begin as early as June 29, 2026. This work will help keep the road smooth, last longer, and make your daily drive more comfortable.

No major changes to the design of the road are expected. The same number of lanes will remain when the project is completed.

 

What to Expect:

Impacts will include traffic shifts, lane closures, intermittent access limitations and an increase in nighttime noise. Bike lanes will be closed and there will be no on-street parking during construction. Drivers should expect delays and use alternate routes when possible. 

 

What you’ll see after construction:

  • A smoother roadway built to last another 5–10 years
  • Improved safety for all road users 

 

This is the project area map of the repaving of 700 East between 400 South and 1700 South

Construction Timeline

Construction timelines are often unknown and are subject to change due to funding.

Project Timeline

planned
planned

Construction: Spring - Fall 2026

Monday - Saturday

8 p.m. to 6 a.m.

complete
complete

Advertisement: March 28 - April

The project will be advertised to contractors beginning in late March 2026.

complete
complete

Design: Fall 2025 through Spring 2026

The team designed improvements and reached out to any potential property owners about impacts. 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 855-925-2801 #12095

Email: 700epaving@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.