5600 West | 3100 S. to SR-201 | West Valley City | Paving

5600 West | 3100 S. to SR-201 | West Valley City | Paving

To extend the life of 5600 West, the Utah Department of Transportation (UDOT) will remove and replace the asphalt and upgrade the ADA pedestrian ramps along 5600 West between 3100 South and SR-201 in West Valley City. This project is scheduled to start on Monday,  June 1, 2026 with completion anticipated in September 2026.

5600 West is a heavily travelled thoroughfare through West Valley City and connects to SR -201. Additionally, this route connects motorists with many shopping destinations, and other business and residential areas.  

Overview

Project Overview

To extend the life of 5600 West, the Utah Department of Transportation (UDOT) will remove and replace the asphalt and upgrade the ADA pedestrian ramps along 5600 West between 3100 South and SR-201 in West Valley City. This project is scheduled to start on Monday,  June 1, 2026 with completion anticipated in September 2026.

5600 West is a heavily travelled thoroughfare through West Valley City and connects to SR -201. Additionally, this route connects motorists with many shopping destinations, and other business and residential areas.  

Heavy traffic and Utah’s four seasons take a toll on our roads and 5600 West needs repairs to the road and upgrades to make the ADA pedestrian ramps compliant with current standards. Once completed, this project will ensure pedestrians, bicyclists, and motorists will have access to fully compliant facilities that are in good repair and ready to last another 5-10 years. 

Project Map

Map of the project area on 5600 West

 

Project Timeline

Construction of the project is expected to begin in June 2026, with anticipated completion in September 2026.

Schedule

Pedestrian ramp reconstruction

Work Hours:  7 a.m. -  5 p.m.*

Asphalt paving

Work Hours:  9 p.m. -  6 a.m.*

Workdays: Monday - Friday

*Schedules are subject to change due to weather conditions and material availability.

Contact Information

Hotline: 855-925-2801 #1394

Email: 5600Wpaving@utah.gov

Project Timeline

live
live

Construction

Construction began on June 1.

 

Project Activities:

  • Final punch list items will be completed by the end of October. All major items have been completed on the project. Final items will include clean up and sweeping project wide. Shoulder closures may be needed to remove construction debris from gutters.

*Schedules are subject to change due to weather conditions and material availability.

planned
planned

Construction End: October 30, 2026

complete
complete

Design

Design was completed in late 2025.

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.