The Utah Department of Transportation (UDOT) and Murray City are working together to make safety improvements and improve traffic flow at the intersection of 5300 South and College Drive. This work will include widening both 5300 South and College Drive, adding an additional left-turn lane and a right-turn-only lane on 5300 South and an additional left-turn lane on College Drive. The project will also include new sidewalks in some areas as well as updated signals for the intersection.

Project Activities:

 

  • Work will begin Monday, May 15*, with the removal of the concrete median along 5300 South. This work will take place from 7 a.m. to 5 p.m. Area residents can expect an increase in noise, vibrations, and work trucks in the area during this work. 
  • Impacts will include lane closures and traffic shifts as well as a planned 35-day closure of the north side of 5300 South at College Drive. During this closure, drivers will be detoured to 700 West/Murray Boulevard.

*schedules are subject to change due to weather, material availability, etc.

Schedule

live
live
Construction

Construction is planned to begin Monday, May 13. Work will take place daily M-F from 6 a.m. to 5 p.m.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 888-556-0232

Email: 5300south@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Subscribe" in the subject line.