3900 South | Jordan River to West Temple | Trail

3900 South | Jordan River to West Temple | Trail

The 3900 South Trail project, a UDOT, Millcreek, and South Salt Lake collaboration, will build a shared-use trail on 3900 South (Jordan River Trail to West Temple). Construction is scheduled for 2026 and 2027.

Overview

Project Overview

Millcreek, South Salt Lake, and the Utah Department of Transportation (UDOT) are building a trail on 3900 South between the Jordan River and West Temple. The trail will provide a safer, more comfortable space for people walking, biking, and rolling, and will connect to future and existing bike lanes.

Pavement preservation from 700 West to the TRAX line will take place with this project. This section of the road will be resurfaced to improve the driving surface and extend the life of the pavement.

This project is part of the Utah Trail Network, a statewide system connecting Utahns of all ages and abilities to destinations and communities through non-motorized, paved trails. For more details about the Utah Trail Network, or UTN, visit utahtrailnetwork.udot.utah.gov.

3900 South Trail project, a collaboration between the Utah Department of Transportation, Millcreek, and South Salt Lake City, is in the final stages of design with construction anticipated in 2026. This section of trail will be built on the south side of 3900 South between the Jordan River Trail and West Temple.

What to Expect

Impacts

  • At least one travel lane will be open in each direction at all times

    • All eastbound lanes will be open weekdays, 6-11 a.m.

    • All westbound lanes will be open weekdays, 1-7 p.m.

  • Intermittent traffic shifts and lane closures

  • Intermittent UTA bus stop closures

  • Limited access to driveways in some areas

  • Reduced on-street parking in some areas

  • Increased noise, dust and vibration

  • Potential for night and weekend work

Schedule

Construction is anticipated to take place in 2026 and 2027.

  • Phase 1: Jordan River to 500 West

    • August-Winter 2026

  • Phase 2: 500 West to West Temple

    • Spring-Summer 2027

Anticipated working hours: Monday-Friday, 7 a.m.  5 p.m.

Project Map

Map of 3900 South showing the future trail from the Jordan River to West Temple. UDOT PIN 21908

 

Project Timeline

planned
planned

Construction

  • Phase 1: Jordan River to 500 West

    • Anticipated Summer-Winter 2026

  • Phase 2: 500 West to West Temple

    • Anticipated Spring-Summer 2027

complete
complete

Completed Project Milestones

  • Concept Development: Completed Fall 2023

  • Public Open House: Held Fall 2023

  • Preliminary Design: Completed Fall 2024

  • Environmental Analysis: Completed Winter 2025

  • Final Design: Completed Summer 2026

Stay Informed

This project will send notifications about upcoming public meetings and updates during construction. Please contact our team if you have any questions or would like to receive updates.

Hotline: 385-386-3806

Email Address: 3900SouthTrail@utah.gov

Website: udotinput.utah.gov/3900southtrail