Project Description:

The Utah Department of Transportation (UDOT) will resurface State Route 171 (3300 S.) in Salt Lake County from Highland Drive to 2700 E. The project objectives are aimed at preserving the life of the road. This paving process will help increase the longevity of the road surface and enhance motorist safety by resmoothing asphalt. Additional work includes upgraded pedestrian ramps to meet ADA compliance, refreshed lane and road painting/striping, as well as updated roadside signage.

Please stay tuned for additional information as it becomes available.

 

11/21  NOTICE: Crews will continue through Wednesday, Nov. 27 restoring utility covers in the road to be flush with pavement.  Some miscellaneous drainage work will continue at intersections.

See "Impacts & Updates" tab for traffic control information.

School crosswalk notification, Westbound approaching 2000 E - 10/31

 

3300 S Paving 1

Center turn lane milling and paving - 10/23

 

3300 S Paving 2

Eastbound lane paving near 2700 E - 10/21

Curb ramp and waterway rebuild

Curb and waterway rebuild - 9/27

 

3300 S Curb ramp rebuild

3300 S Pedestrian Ramp Construction - 9/25

 

SR-171 Ped Ramp Rebuild

3300 S Pedestrian Ramp Construction - 9/11

 

 

Schedule

complete
complete
Design: Winter/Spring 2024

  • June: Project advertised for contractor bid
  • July:  Contractor awarded

live
live
Construction: Tuesday, Sept 3

Work Hours: Daytime Hours (Sunrise - Sunset)

Workdays: Sunday - Thursday (Fri/Sat as necessary)

Project Duration:  Approximately 75 days

Schedules are subject to change due to weather conditions and material availability.

 

Sept. 3 - Oct. 10 [Complete]:  Pedestrian ramp rebuilds for ADA compliance.

Sept. 16 - 25 [Complete]:  Utilities to be lowered within the road in preperation for paving

Oct. 13 - 24 [Complete]:  Paving operations.  Travel lane lines and road surface directional striping will occur during this time as well.  Please see "Impacts & Updates" tab for traffic control information.

Through Nov 14:  Road surface striping, raising utility covers to be flush with road, and miscellaneous work.

Nov 12 - 27:  Raising uility covers to be flush with pavement.  Updating roadside signs and some drainage enhancements

 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8362

Email: 3300southpaving@utah.gov

Stay Informed

To recieve construction updates, please contact the public informaiton team at the email address above and enter "Updates" in the subject line.