2100 South | West Temple to Main St. | Improved

2100 South | West Temple to Main St. | Improved

This project will upgrade traffic signals and road lighting at the intersections of 2100 S & West Temple and 2100 S & Main St. The pedestrian ramps at the intersections will also be upgraded.

Overview

Project Overview

UDOT is upgrading traffic signals and road lighting at two intersections in South Salt Lake. These improvements will make the intersections safer and easier to use for all road users. The pedestrian ramps at the intersections will also be upgraded.

Project Locations

  • 2100 South (SR-201) & West Temple
  • 2100 South (SR-201) & Main St.

Planned Improvements

  • New traffic signal equipment, including signal heads and mast arms (the poles that hold signals over the road)
  • Audible pedestrian push buttons, which use sound and touch cues to help people who are blind or have low vision cross safely
  • Rebuild pedestrian ramps that meet Americans with Disabilities Act (ADA) standards

What to Expect

  • Sidewalk closures: Sidewalks will close at times while crews rebuild the ramps. Follow the posted detour signs.
  • Shoulder closures: Most work will only need the road shoulder to be closed.
  • Short lane closures: Crews may close a lane for about an hour at a time, for example, to locate underground utilities.
  • Signal changeover: Switching to the new signals and mast arms will require lane closures for about 2-3 days at each intersection.
  • Stay alert: Please slow down and watch for crews working close to traffic.

Project Map

Construction will take place on 2100 S & West Temple/Main St. to upgrade the traffic signals and road lighting.

Schedule Work

Hours: 8:00 a.m. - 4:30 p.m.

Workdays: Monday - Friday

 

*Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

Construction

  • Preparation work for the replacement of the older intersection technology

planned
planned

Replace Traffic Signal Equipment

  • Replace the current mast arms and traffic signals with new mast arms and traffic signals
  • The project is expected to be done by early December

complete
complete

Milestones

  • Items will be added as the project team completes them.

Contact Information

Hotline: 833-819-6776

Email: 2100southimproved@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.