1600 North | Lindon & Orem | Improved

1600 North | Lindon & Orem | Improved

Impacts & Updates

Impacts and Updates

Intermittent Side Road Closures for Paving

Crews will pave the south side of 1600 North beginning on Sunday, Nov. 15, through Wednesday, Nov. 18. As part of this work, rolling, intermittent closures will be necessary at the following intersections along 1600 North:

  • 1100 West 
  • 1040 West
  • 950 West
  • 800 West
  • 740 West
  • 650 West

Flaggers will be stationed at the entrance of each intersection between 7 a.m. and 7 p.m. each day to direct traffic. Please use caution and expect travel delays.

Map showing flagging at the intersections along 1600 North, including at 1100 West, 1040 West, 950 West, 800 West, 740 West, and 650 West.

Construction schedules are dependent on multiple factors and are subject to change.

 


1150 West Closed
 

1150 West will be closed at 1600 North through Wednesday, Nov. 18, for crews to perform utility work and complete paving on the south side of the road. 1600 North will remain open in both directions and driveway access will remain open to residents. Please use 1200 West as an alternate route.

Map showing 1150 West closed at 1600 North in Orem.


No Parking Along 1600 North

Reminder: No parking is allowed along 1600 North within the work zone. Please keep the shoulder clear so crews have enough space to work safely. 

Map showing the no parking area along the shoulder of 1600 North in Orem

 

 

 

Schedule

Work Hours: 7 a.m. to 6 p.m.

Workdays: Monday – Friday 

Weekend work will take place as needed

Construction schedules are subject to change due to a variety of factors. 

Project Timeline

complete
complete

State Environmental Study: 2021-2023

Read SES information for this project. 

complete
complete

Design and Right-of-Way Acquisitions: 2023-2026

Resources explaining UDOT’s right-of-way process.

live
live

Construction: Spring 2026 - Late Fall 2027

Construction began Wednesday, March 25.

See Impacts & Updates tab for more information.

Construction schedules are dependent on a variety of factors and subject to change.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-406-7707

Email: 1600North@utah.gov

Stay Informed

To receive project updates, email 1600North@utah.gov and enter "Updates" in the subject line.