UDOT plans to widen the roadway on SR 252 (10th West) from a 3-lane road to a 5-lane road in the section from 1400 North to 2500 North, as well as add a dual left turn from 2500 North (Airport Road) to 10th West.

Overview

Project Overview

The Utah Department of Transportation (UDOT) is planning to widen the roadway on SR 252 (10th West) from a 3-lane road to a 5-lane road in the section from 1400 North to 2500 North. The intersection at 10th West and 2500 North (Airport Road) will also be modified to accommodate dual left-turn lanes from the westbound lanes on 2500 North westbound (Airport Road) to 10th West southbound. Curb and gutter will not be added as part of this project.

Project Map

Map detailing the study area running along 1000 West (SR-252), extending from 1400 North to and onto 2500 North next to the Logan-Cache Airport.

Project Timeline

Project timeline detailing the project milestones between now and Fall of 2028.

 

Schedule

Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

Initial Design and Field Surveys - Summer 2026

  • Field surveys will be conducted to identify potential biological and cultural resources along portions of 10th West and 2500 North. This effort will involve taking photographs and measurements and reviewing vegetation and wildlife. 
  • The Design team will be working on initial drainage and roadway designs.
  • The design team will also assess if any right-of-way agreements need to be acquired.

planned
planned

Construction to begin in Summer 2028

  • The project team will obtain any needed right-of-way agreements through the summer of 2027.
  • Needed permits will be obtained through the summer of 2027
  • Engineers will finalize designs by September 2027
  • A contractor will be selected in the winter months of 2027-2028
  • Construction is expected to begin in the summer of 2028.

complete
complete

Project Milestones

  • Design will be completed in September 2027
  • Construction is expected to be completed in the fall of 2028.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 800-970-4843

Email: 10thwestwidening@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.